Engineering Change Management工程变更管理程序(中英文).docx
《Engineering Change Management工程变更管理程序(中英文).docx》由会员分享,可在线阅读,更多相关《Engineering Change Management工程变更管理程序(中英文).docx(6页珍藏版)》请在第一文库网上搜索。
1、Approval批准Reviewer审核Originator作成Change History变更记录Revision版本Effective Date生效日期Originator编写人Reasons for Change修改原因1.02012-1-1Initial release/初次发行2.02021-5-11 Update the ECN application for developing phase/开发阶段的变更也需要遵照ECN流程1.0 PURPOSE 目的1.1 Establish the procedure for engineering change to change the
2、 specification, material and process,and ensure daily production in line.建立工程变更的程序,明确职责,使产品的规格、材质、工艺等变更有标准可依,以保证生产正常有序地进行。2.0SCOPE 范2.1 Apply to product specification, material, process and any other engineering change in massproduction.适用于产品开发和量产过程中产品规格、材质、工艺流程或其他工程相关的变更。3.0 DEFINITIONS 定义3.1 ECR:
3、Engineering Changing Request 工程变更申请3.2 ECN: Engineering Changing Notice 工程变更通知4.0 REFERENCE DOCUMENTS 参考文件Non无5.0 RECORDS 记录5.1 FN-AQ-001 Engineering Change Notice 工程变更通知5.2 FN-AQ-006 Engineering Changing Request 工程变更申请单6.0 RESPONSIBILITY 职责6.1 AQP department release ECR for customer engineering cha
4、nge; Lead to evaluate ECR;Communicate with customer for the disposal of products and confirm the cost owner, and claimform customer.项目部负责提出客户变更的工程变更申请;主导ECR的评估,与客户协调变更前产品的处理;与客户确认变更所需的费用和请款。6.2 AQP department release ECR for engineering change; Lead to evaluate internal ECR andtrace the ECN;项目部负责提出与
5、工程相关的工程变更申请;主导内部工程变更的评估和进度追踪;6.3 Purchase department release ECR for supplier change; Report current stock, including insupplier, WIP, warehouse and PO; implement ECN action.采购部负责提出与供应商相关的工程变更申请;提报现有库存状况(供应商存货,在制品数量的收集,仓库成品,不可取消的订单);执行工程变更动作。6.4 Production department release ECR for production chang
6、e; Count the quantity in WIP; implementECN action.生产部负责提出与生产相关的工程变更申请;提报生产现场在制品数量,执行工程变更动作。6.5 Quality department release ECR for quality issue; Evaluate measuring instruments and fixture;Update SIP, control plan, measuring instruments, fixture and etc. DCC distribute ECN.质量部负责提出与品质相关的工程变更申请;负责评估测量仪
7、器和检具,以及变更后相关检验规范、控制计戈上测量仪器和检具等变更。文控负责工程变更通知的发行。7.1 PROCESS 流程7.1 Issue ECR工程变更申请的提出7.1.1 Customer Required ECR客户要求的工程变更AQP issue ECR for customer change(Product/Capacity,etc) and lead to evaluate ECR.项目部接到客户变更需求(产品/产能等时,提出ECR,组织相关部门评估。Internal ECR内部需求的ECRA) Each department could issue ECR when neces
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- Engineering Change Management工程变更管理程序中英文 Management 工程 变更 管理程序 中英文