化工厂检修开停工安排统筹图及说明.docx
《化工厂检修开停工安排统筹图及说明.docx》由会员分享,可在线阅读,更多相关《化工厂检修开停工安排统筹图及说明.docx(6页珍藏版)》请在第一文库网上搜索。
1、化工厂检修开停工安排统筹图及说明化工总体网络统筹安排见下表:序名装置名称计划天数停工时间检修时间待料时间停工检修开工待料合计1化工一裂解92770435.85.175.17-6.1302乙二醇226213435.8-5.105.106.56.5-6.183制苯预分储83034455.65.145.14-6.136.13-6.174加氢93360485.65.155.156.1705碳六抽提83144475.65.145.146.146.146.186碳八抽提1030107575.55.155.156.146.14-6.217苯乙烯62368435.85.145.146.66.66.148碳五装
2、置717625195.17:00-5.85.85.255.25-6.199化工二一聚丙烯526418534.285.35.35.295.29-6.161O二聚丙烯52649445.7-5.125.126.76.7-6.1620:0011三聚丙烯52649445.7-5.125.12-6.76.76.1620:0012化工三一苯酚82756465.55.135.136.96.9-6.1513苯酚氧化、精制82756465.55.135.13-6.96.96.1514大煌化IO2779534.28-5.85.86.46.4-6.1315化工六高压一线13462435.87:005.95.9-6.1
3、26.12-6.1316二线13462435.85.95.9-6.126.12-6.1317三线13465465.55.65.66.96.9-6.1418低压A线52854435.87:00-5.135.13-6.106.10-6.1519B线52855445.77:00-5.125.12-6.96.9-6.152O二高压33524445.75.105.10-6.146.14-6.182化工八间二甲苯72586465.710:00-5.146.86.8-6.M15.1422氧化42552365.8-5.125.12-6.66.66.8231己烯617829605.710:00-5.135.13
4、5.305.306.2924橡胶厂抽提520513435.8-5.135.13-6.26.2-6.1525乙脑519513425.9-5.145.146.26.2-6.1526顺丁装置51866355.10-5.155.15-6.26.26.827顺丁后处理52135345.115.165.16-6.66.6-6.1128SBS装置518614435.8-5.135.13-5.315.31-6.1429SBS后处理521313425.9-5.145.14-6.46.4-6.173O稀土顺丁518616455.65.115.11-5.295.29-6.1431异虎橡胶518624535.35.8
5、5.85.265.266.1932MTBE合成52845425.9-5.145.146.116.11-6.1633MTBE裂解520317455.65.115.115.315.316.17344.5万吨丁基橡胶425610455.65.105.106.46.4-6.143510万吨异丁烯524316485.55.105.106.36.3-6.19369万吨丁基422616485.55.95.95.315.316.1637有机厂VAE系列38I1VAC115228465.6-5.75.75.225.22-6.19392,VAC4OEVA装置221517455.75.95.95.305.30-6.