1、井下作业英语100句The tractor hoist should be located behind the derrick.通井机应就位在井架后面。The tubing bridges are arranged in three (3) lines.摆放油管架,三行。The line spacing is three meters.行距为3米。The tubings are arranged in groups of ten(10) joints and marked properly.排放油管,十根一组,做好标记。The wellhead protecting cap is remov
2、ed and the riser and the X-tree are installed.卸井口帽,安装升高短节及采油树。Be sure the thread is coated with sealing grease and the bolts are tightened.保证螺纹涂密封脂,螺栓上紧。You must break out all the large bolts on the wellhead.你们必须卸掉井口大螺栓。All the large bolts in the well head been broken out?井口大螺栓卸掉了吗?Remove the upper
3、valving of X-tree above the spool.抬开大四通以上采油树闸门部分。The tubings are measured and drifted by the tubing gauge after the tubing measurement is recorded.丈量油管,整理好油管记录后,要用油管规通油管。Latch on the elevator securely.扣好吊卡。Dont use only one elevator link.不能挂单吊环。Trip the tubing string up and down.上下活动油管。The reading c
4、hange of weight indicator is to be observed carefully.注意观察指重表读数变化。Run the flush tubings first, and then the EUE(external upset end) tubings.Connect then with a cross-over joint.先下平式油管,再下加厚油管,二者用变扣短节连接。The speed should be reduced when the tubing string is running near the bottom of the hole.管柱接近井底时减缓
5、下钻速度。10KN is loaded to detect the bottom of the hole.探井底时加压10千牛。What is the pressure to be used to detect the bottom of the hole?探井底时加多大压力?Pull out one joint of tubing first, and then install the tubing hanger.先上提一根油管,再坐好油管挂。Make up and tighten the bolts diagonally when the X-tree is installed.安装采油树
6、是要对角上紧螺栓。Now connect the flowback line from a casing valve to the storage pit or storage tank.现在从套管闸门接出一根放喷管线到储液池或储液罐。Put the end of the suction hose of the pump truck into the fresh water tank.把泵车吸水端插入清水罐。The high pressure discharge pipe of pump truck is connected with a producing valve of the X-tr
7、ee.泵车高压输出管线接到生产闸门上。Open the production valve and the casing valve.打开生产闸门和套管闸门。Dont open the production valve now.现在不要打开生产闸门和套管闸门。Display the mud in the wellbore with fresh water down the tubing and circulate the well.用清水正替换井筒泥浆,洗井。If any sticking happens during pulling the tubing, the cause should b
8、e found out before any decision making.提油管时如果中途遇阻,找出原因后再做决定。The wellbore is tested to the pressure of twelve (12) MPa.井筒正试压12兆帕。What pressure is the wellbore tested to?井筒正试压多大?Pull out the drifting string and check the gauge for scratch.起出通井管柱,检查通井规擦痕。Help the perforating crew to hoist the pulley fo